Opens in a new tab
Cable Sizing

Earth Fault Loop Impedance BS 7671

Learn the difference between Ze and Zs, calculate earth fault loop impedance from R1 + R2, and check disconnection under BS 7671 with a worked example.

Updated November 9, 2026

Earth fault loop impedance (Zₛ) is the impedance of the complete path the fault current takes from the source, along the line conductor, through the fault, and back to the source via the protective return path. It determines whether enough current can flow for the protective device to disconnect the supply within the time required by BS 7671.

For a TN circuit where the reactance of the installation circuit is small enough to neglect, a practical estimate is Zₛ ≈ Zₑ + (R₁ + R₂). All quantities are in ohms (Ω).

What are Zₑ, Zₛ, R₁ and R₂?

  • Zₑ is the impedance of the part of the earth fault loop external to the installation.
  • Zₛ is the impedance of the complete loop at the point under consideration, including the external path and the installation circuit.
  • R₁ is the resistance of the line conductor up to that point.
  • R₂ is the resistance of the circuit protective conductor (CPC) back from that point.

For design, obtain a suitable Zₑ value from the distribution network operator (DNO). For verification, establish Zₑ at the installation origin by measurement or another valid method. A DNO-supplied value alone does not confirm that the installation is connected to earth. IET guidance on supply characteristics and verification

TN-C-S earth fault loop showing external impedance Ze, line impedance Z1 and CPC return impedance Z2
TN-C-S example. During a line-to-case fault, current returns through the CPC and the supply PEN conductor. Zₛ covers the complete loop.

Why use R₁ + R₂ if the loop carries AC?

For the simplified loop shown, Z₁ = R₁ + jX₁ is the line-path impedance and Z₂ = R₂ + jX₂ is the protective return-path impedance. X₁ and X₂ represent the reactance of those paths. Where complex impedance data are available, add the external and circuit impedances as complex quantities, then take the magnitude: Zₛ = |Zₑ + Z₁ + Z₂|. This expression treats Zₑ inside the magnitude as a complex impedance.

For BS 7671 verification, you can obtain R₁ + R₂ with a dead continuity test. It is straightforward to measure, and adding it to the external loop impedance reading gives a practical estimate of Zₛ for many TN circuits. The approximation replaces the circuit’s AC impedance with its measured resistance and adds that resistance to the magnitude of Zₑ. It can differ from a full calculation where reactance is significant. Check the actual return path, especially where armour or parallel protective paths are involved, and include reactance where it affects the result. IET guidance on initial verification · IET guidance on resistance, reactance and temperature

BS 7671 disconnection times at 230 V AC

For 230 V line-to-earth AC final circuits within the scope of Regulation 411.3.2.2 and Table 41.1, including final circuits rated up to 63 A with one or more socket-outlets and up to 32 A supplying fixed equipment only, the general maximum disconnection times are:

  • TN: 0.4 s for final circuits covered by Table 41.1. The general limit for distribution circuits and other circuits outside that scope is 5 s.
  • TT: 0.2 s for final circuits covered by Table 41.1. The general limit for distribution circuits and other circuits outside that scope is 1 s.

For other voltages or arrangements, check the applicable requirements and exceptions in BS 7671:2018+A4:2026. The disconnection time is a circuit requirement. The maximum Zₛ for an overcurrent device depends on the device characteristics and the current needed to operate it within that time. Current BS 7671 edition

For a TN circuit where an overcurrent protective device provides fault protection, check that:

Zₛ × Iₐ ≤ U₀ × Cₘᵢₙ

Iₐ is the current that ensures the device operates within the required disconnection time, U₀ is the nominal line-to-earth voltage, and Cₘᵢₙ is the minimum voltage factor. Rearranging gives the maximum permitted Zₛ as U₀ × Cₘᵢₙ / Iₐ.

Worked example: 230 V TN circuit with a Type B 32 A circuit-breaker

Assume a 230 V TN final circuit supplying socket outlets is protected by a 32 A Type B circuit breaker to BS EN 60898-1. Its required disconnection time is 0.4 s. Use an external loop impedance of 0.25 Ω and a circuit resistance R₁ + R₂ of 0.55 Ω at 20 °C. For this example, assume the conductor resistance at the operating temperature is 1.20 times the 20 °C value and neglect circuit reactance.

  1. Estimate Zₛ at operating temperature. Zₛ ≈ 0.25 + (0.55 × 1.20) = 0.91 Ω.
  2. Find the device limit. Using Iₐ = 5 × 32 A = 160 A and Cmin = 0.95 for this example, the limit is U₀ × Cmin / Iₐ = 230 × 0.95 / 160 ≈ 1.37 Ω. U₀ is the nominal line-to-earth voltage, and Iₐ is the current that ensures operation within the required time.
  3. Compare on the same basis. The design estimate of 0.91 Ω is below the device limit of 1.37 Ω for this example.

Use the appropriate BS 7671 table or manufacturer’s data for the device and its settings. An ambient loop test and a design calculation at operating temperature use different temperature assumptions. The IET On-Site Guide gives 80% values as a quick check for applicable ambient measurements. A result close to or above that screening value calls for a more detailed temperature assessment. IET guidance on interpreting maximum Zₛ values

What changes for TT and RCD fault protection?

In a TT system, the earth return includes the installation earth electrode and the path through earth. Where an RCD provides fault protection, check both the required disconnection time and Rₐ × IΔn ≤ 50 V under the general BS 7671 condition. Rₐ is the combined resistance of the installation earth electrode and the protective conductor connecting it to the exposed-conductive-parts. IΔn is the RCD’s rated residual operating current. Apply the requirements for the particular installation and verify RCD operation. IET guidance on TT earthing

Protective conductor and device checks

Where the return path uses armour, a separate protective conductor or parallel paths, use the impedance of the actual arrangement. Check CPC selection and thermal withstand separately, alongside the protective-device disconnection check.

For three-phase short-circuit studies, see IEC 60909 Fault Calculations.

   

Related Articles